Dan Burroughs
- May 6, 2023
- 1 min
W. LaBonte milling complete
Columbine Hills completed the milling operations on W. LaBonte Street between Lake Dillon Drive and the Dillon Dam Road yesterday. The...
18 views0 comments
Dan Burroughs
- May 2, 2023
- 1 min
Lodgepole St. Sanitary Sewer Main Complete
The contractor finished the replacement sanitary sewer main on Lodgepole Street yesterday afternoon. Tomorrow, they will start on the...
29 views0 comments
Dan Burroughs
- Apr 30, 2023
- 1 min
Sanitary Sewer Main Replacement nears completion
In spite of the forecast for big snow storms last week, the contractor was able to lay the rest of the Lodgepole Street sewer pipe and...
32 views0 comments
Dan Burroughs
- Apr 24, 2023
- 1 min
Sanitary Sewer Work Continues on Lodgepole
We lost one-day last week due to the snow. This week the contractor should have more than half of the sanitary sewer replacement...
28 views0 comments
Dan Burroughs
- Apr 19, 2023
- 1 min
W. LaBonte Intersection OPEN at Lodgepole to LaBonte Traffic
The contractor completed their work in the intersection this afternoon and installed a temporary asphalt milling surface over the work...
18 views0 comments
Dan Burroughs
- Apr 14, 2023
- 1 min
LaBonte Closure at Lodgepole/W. Buffalo
Starting Monday morning, April 17th, at 7:00 am, the intersection at W. LaBonte Street and Lodgepole/W. Buffalo Street will be closed for...
44 views0 comments
Dan Burroughs
- Apr 14, 2023
- 1 min
Lodgepole Street Work underway
The contractor, Columbine Hills Construction, had a good first week of construction. Weather cooperated. They were able to complete the...
31 views0 comments