Tenderfoot Update
The contractor completed most of the asphalt paving today, but the rain cut it short. Next week, the contractor will finish the asphalt...
35 views0 comments

Dan Burroughs
- Jul 8, 2022
- 1 min
Tenderfoot Hill Update
The contractor finished most of the sidewalk this week. They have a few tie-ins to complete Monday morning at the bottom of the hill.....
34 views0 comments

Dan Burroughs
- Jul 1, 2022
- 1 min
Tenderfoot Hill Update
The contractor was able to complete the first asphalt lift yesterday in spite of the rain. The contractor is not working today or Monday....
32 views0 comments

Dan Burroughs
- Jun 29, 2022
- 1 min
Tenderfoot Hill Paving on Thursday
The contractor has imported, placed and compacted the roadbase on Tenderfoot Hill. Today they are adjusting the manhole lids to the top...
25 views0 comments

Dan Burroughs
- Jun 24, 2022
- 1 min
Saturday Work on Tenderfoot Hill
To keep up with next week's Concrete and Asphalt schedule, the contractor will be placing and compacting roadbase on Tenderfoot Hill...
31 views0 comments

Dan Burroughs
- Jun 24, 2022
- 1 min
Road Stabilization Completed
The contractor completed the stabilization of the Tenderfoot Hill along the highway side this afternoon. We had to dig down 2' and...
9 views0 comments
Dan Burroughs
- Jun 10, 2022
- 1 min
Water Outage Tuesday June 14th - Tenderfoot Hill
The contractor is planning to replace a fire hydrant near the top of Tenderfoot Hill on Tuesday next week. TUESDAY - JUNE 14TH, 2022. The...
19 views0 comments
Dan Burroughs
- Jun 7, 2022
- 1 min
Water Outage: Thursday June 9th
The contractor is planning to replace a fire hydrant near the top of Tenderfoot Hill on Thursday. The water will be off from 9am-6pm. The...
23 views0 comments

Dan Burroughs
- Jun 3, 2022
- 1 min
Concrete Sidewalk Construction in Progress on Tenderfoot
The contractor made great progress this week on the sidewalk between the two ends of Gold Run Circle. Most of the concrete valley pan is...
21 views0 comments

Dan Burroughs
- Jun 2, 2022
- 1 min
Friday June 3rd: Start pouring the concrete sidewalk
Tomorrow on Friday June 3rd, The Contractor will start pouring the sidewalk between the gold run circle ends.
8 views0 comments

Dan Burroughs
- May 13, 2022
- 1 min
Traffic Patterns Week of May 16th
The contractor, 360 CIVIL, will start working on the Tenderfoot Street project on Monday, May 16th, 2022. The map below indicates the...
38 views0 comments