06.01.2022 Concrete Work On Tenderfoot between Gold RunsDan BurroughsMay 31, 20221 min readTomorrow, the contractor plans to pour the concrete valley pan on the lakeside of Tenderfoot between the two ends of Gold Run Circle.
Tenderfoot Street paving half doneThe contractor completed the north side (Highway side) of the asphalt paving today. And they completed the south side (Lake side) between highway 6 and the Anchorage East driveway. Tomorrow on Thursda