Concrete progress on E. Labonte Street

Dan Burroughs
Aug 13, 2021
1 min read

The contractor made great progress this week on the concrete work.

Columbine Hills Construction completed:

  • Concrete Pans on the two southern corners of the intersection at Tenderfoot & LaBonte

  • Concrete Pan along the north side of the intersection.

  • Concrete sidewalks adjacent to the intersection.

  • Concrete curb and gutter and concrete pans along the west side of LaBonte Street between the Tennis courts and the Museum.

  • New concrete work around the museum parking lot.

The contractor installed the roadbase and prepared the remaining sidewalk areas along the west side of LaBonte Street.


 
 
Dan Burroughs, P.E.
Town Engineer

Town of Dillon, Colorado