  • Dan Burroughs

Concrete Sidewalk Construction in Progress on Tenderfoot

The contractor made great progress this week on the sidewalk between the two ends of Gold Run Circle. Most of the concrete valley pan is complete and about 60% of the sidewalk is finished in this section.




21 views

Recent Posts

See All

The contractor completed most of the asphalt paving today, but the rain cut it short. Next week, the contractor will finish the asphalt work and complete the installation of topsoil and start cleaning