Getting ready for curb and gutter

  • Dan Burroughs
  • May 27, 2021
  • 1 min read

The contractor made great progress this week and finished all the utility work. The contractors stabilized a few soft spots in the subgrade this week. The contractor prepped the north and south sides of the road and the parking lot for curb and gutter. If the weather holds out the concrete curb and gutter will start going in on Friday, tomorrow.


 
 
 