Columbine Hills made good progress this past week and installed about half of the storm sewer main in Lodgepole Street staring at W. LaBonte Street. Next week they will jump down to the south end of West Buffalo and install the storm sewer pipe and manholes between the outfall pipes and the new system and build a storm sewer across the LaBonte Street intersection with Lodgepole Street.


New Inlet installation next to Lake Dillon Condominiums:

ree


New Double Area Inlet installation at the bottom of Lodgepole Hill next to Lake Dillon Condominiums: