May 12, Wednesday Paving Schedule: Village, Schroeder and Main Street

  • Dan Burroughs
  • May 11, 2021
  • 1 min read

Well, we got through another May snowstorm.

Wednesday and Thursday should have good weather. Here is the revised paving Schedule.


Wednesday (May 12th): the Contractor will pave these streets in the following Order

1) VILLAGE PLACE (Starts around 7:30 am)

2) SCHROEDER

3) MAIN STREET


LA RIVA DEL LAGO RESIDENCES:

The Main Street entrance will be blocked for 3-4 hours while the paving crew is working on this section of Main Street. Please plan to park your vehicles in a nearby parking lot, if you will need your vehicle between 11am and 6pm.


Thursday (May 13th): the Contractor will pave these streets in the following Order

1) FIEDLER AVENUE (Starts around 7:30 am)

2) MAIN STREET - - Remaining Portion if needed


NOTE: On-street parallel parking & diagonal parking will be CLOSED on paving day.



 
 
 

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
Dan Burroughs, P.E.
Town Engineer

Town of Dillon, Colorado

970.418.2544

danb@townofdillon.com

© 2021 by Town of DIllon, Colorado . Proudly created with Wix.com

bottom of page