Milling operations are under way this morning. Contractor is making good progress. Village and Schroeder are done and they are in the cleanup phases on those two Streets.
The contractor completed the north side (Highway side) of the asphalt paving today. And they completed the south side (Lake side) between highway 6 and the Anchorage East driveway. Tomorrow on Thursda