North Dam Road Milling on Wednesday 9/15.

Dan Burroughs
Sep 10, 2021
1 min read

The Town has hired Columbine Hired Construction to resurface North Dillon Dam Road and rebuild Dillon Ridge Road to the east adjacent to the new medical center facility under construction.


WEDNESDAY 9/15: The contractor will remove the top layer of asphalt by milling.


TRAFFIC DETOUR: During the work hours the Dam Road entrance to the shopping center will be closed....all traffic will be detoured west to the Dillon Ridge Road entrance by Alpine Bank and Walgreens.


The PAVING will take place during the following week on Monday and Tuesday... 9/20 & 9/21.

The reconstruction of rest of Dillon Ridge Road east of the intersection will be done between 9/20 and 10/1.


 
 

Recent Posts

See All
Tenderfoot Street paving half done

The contractor completed the north side (Highway side) of the asphalt paving today. And they completed the south side (Lake side) between highway 6 and the Anchorage East driveway. Tomorrow on Thursda

 
 
Dan Burroughs, P.E.
Town Engineer

Town of Dillon, Colorado

970.418.2544