Because of the paving operations in the northbound lanes of Lake Dillon Drive just south of the Tenderfoot intersection, the left turn lane will be closed to facilitate construction and truck movements in and out of the work area. At times the paving chain (Paver and dump truck) will be occupying the northbound lanes of Lake Dillon Drive, and all trucks delivering asphalt have to back into the work area from the Tenderfoot intersection.



 
 

Recent Posts

See All
Tenderfoot Street paving half done

The contractor completed the north side (Highway side) of the asphalt paving today. And they completed the south side (Lake side) between highway 6 and the Anchorage East driveway. Tomorrow on Thursda

 
 