The contractor completed most of the asphalt paving today, but the rain cut it short.


Next week, the contractor will finish the asphalt work and complete the installation of topsoil and start cleaning up.

The contractor will also install a new traffic guardrail on the lake side of the hill.


The road will remain closed next week.

 
 

Recent Posts

See All
Tenderfoot Street paving half done

The contractor completed the north side (Highway side) of the asphalt paving today. And they completed the south side (Lake side) between highway 6 and the Anchorage East driveway. Tomorrow on Thursda

 
 