top of page

Thursday 06.16 Tenderfoot Update

Dan Burroughs
Jun 16, 2022
1 min read

The contractor completed the concrete curb on the lake side of the hill today.

Over the next week, they will be removing the asphalt road on the lower section of the hill and the curb on the highway side of the hill. Next week they will pour the sidewalk along the lakeside of Tenderfoot Hill.




Earlier in the week Civil 360 finished the fire hydrant replacement




 
 

Recent Posts

See All
Tenderfoot Street paving half done

The contractor completed the north side (Highway side) of the asphalt paving today. And they completed the south side (Lake side) between highway 6 and the Anchorage East driveway. Tomorrow on Thursda

 
 
Dan Burroughs, P.E.
Town Engineer

Town of Dillon, Colorado

970.418.2544

danb@townofdillon.com

© 2021 by Town of DIllon, Colorado . Proudly created with Wix.com