Town Center Paving Schedule: Monday (Fiedler & Main) - Tuesday (Village, Schroeder & Main)
- Dan Burroughs
- May 7, 2021
- 1 min read
There is a winter storm forecast for Monday and Tuesday. This may or not affect the paving schedule.

NOTE: On-street parallel parking & diagonal parking will be CLOSED on paving day.
Monday (May 10th): the Contractor will pave these streets in the following Order
1) FIEDLER AVENUE (Starts around 7:30 am)
2) MAIN STREET - Between Schoeder and E. LaBonte.
Tuesday (May 11th): the Contractor will pave these streets in the following Order
1) VILLAGE PLACE (Starts around 7:30 am)
2) SCHROEDER
3) MAIN STREET - Remaining Portion.
LA RIVA DEL LAGO RESIDENCES:
The Main Street entrance will be blocked for 3-4 hours while the paving crew is working on this section of Main Street. Please plan to park your vehicles in a nearby parking lot, if you will need your vehicle between 10am and 5pm.