Work continues....Dan BurroughsApr 24, 20211 min readUpdated: Apr 27, 2021Completed the inlet south of the fire station drive
Tenderfoot Street paving half doneThe contractor completed the north side (Highway side) of the asphalt paving today. And they completed the south side (Lake side) between highway 6 and the Anchorage East driveway. Tomorrow on Thursda