The Concrete has cured and COLUMBINE HILLS CONSTRUCTION was able to backfill against the new concrete wall.
The photo below is the low side of the new loading dock #2. They will be pouring concrete and installing a trench drain in the next few weeks. Dock #1 will still be at grade. Dock#2 will be able to accommodate large semi trucks more efficiently.