The contractor was able to make some good progress this week in spite of the rain. We lost two days last week because of the heavy rain on Thursday and Friday. Rain makes for nice rainbows though.....


The storm sewer through the intersection has been completed and tied into the existing downstream storm sewer in W. Buffalo Street. The photo below shows two of the new manhole installed in the intersection.


Below is a photo of a new storm inlet (catch basin) that will collect drainage from the north drainage pan uphill from West Buffalo Street at the intersection.