Storm Sewer Progress in LaBonte Intersection

Dan Burroughs

The contractor made good progress this week and completed the installation of the storm sewer section through the intersection. Due to weather conditions, they will not work today 5/11. Next week they will finish the downstream storm sewer connection and start prepping the intersection for the new concrete work. The new concrete curbs should be done by next weekend. The paving of the intersection is still scheduled for the week of May 22nd, before Memorial Day Weekend.

The intersection remains closed until Memorial Day Weekend.