W. LaBonte Paving Continues

The contractor was only able to finish about 20% of the asphalt overlay yesterday before the rain.

The photo below is from Wednesday 5/31 at the end of the day.


The plan today is to complete the paving operations between Dillon Dam Road and Three Rivers this afternoon.

Heavy rain is forecast after 1:00 p.m on Thursday 6/1.