Intersection concrete complete
The contractor finished pouring the concrete sidewalks and concrete pans around the intersection at West Labonte Street and Lodgepole...
Dan Burroughs
May 24, 20231 min read
Â
Â
Â


LaBonte/Lodgepole Intersection Progress (with Rain)
The contractor was able to make some good progress this week in spite of the rain. We lost two days last week because of the heavy rain...
Dan Burroughs
May 21, 20231 min read
Â
Â
Â


Amphitheater Loading Dock Progress
The Concrete has cured and COLUMBINE HILLS CONSTRUCTION was able to backfill against the new concrete wall. The photo below is the low...