Road Stabilization Completed
The contractor completed the stabilization of the Tenderfoot Hill along the highway side this afternoon.
We had to dig down 2' and replace the materials with layers of Geogrid materials and imported roadbase.
The project was delayed for several hours this morning because of trucking problems through Silverthorne due to the road closure because of a police incident.