Tenderfoot Hill Update
The contractor was able to complete the first asphalt lift yesterday in spite of the rain.
The contractor is not working today or Monday. They will resume on Tuesday after the Holiday.
Happy 4th of July!
Week of July 5th: Complete Tenderfoot Hill Sidewalk and work behind curbs.
Week of July 11th:
Asphalt Milling of the existing road between lower Gold Run and LaBonte.
Final 2" Asphalt layer in milled areas & Finish driveway connections.
Week of July 18th:
Install guardrail on the lakeside of the hill and project close-out.
All dates are subject to change due to weather and supply chain issues.